The number everyone cites is the backup — and it's redacted
Every summary repeats 313 MW. It is backup generation — 114 emergency gensets — not the operating load, and the per-engine rating that multiplies to it is redacted in the issued permit. So the working draw can only be inferred: 303–393 MW (central ~348), and that inference chain is the uncertainty. Drag it open below. Full essay: the load and the grid →